Wednesday, 1 January 2014

Task Five - Pre-Production Planning


Proposal
Prepared by
Jack Fox
I will be producing a music video to the song 'Take a Walk' by Passion Pit. The band's genre is indietronica and the song is very upbeat. Indietronica is a fusion of the styles rock, pop, electronica, and indie. The song is about taking a walk and moving around. To mirror this action, we have decided to base the video on the idea of travelling. As the song is very upbeat and has a clear bass drum it should be easier to edit to the beat; we have decided to have the singer walk towards the camera in a straight line whilst the background changed on certain beats. The walking towards to camera will only happen in the chorus though, and when the verses are sung the background will change but the singer will stand in the same spot. 


Production Schedule
Part One


Programme Title: Music Video - Take a Walk
Client: Passion Pit
Writer: Jack Fox
Date: 05/02/14

                                                                        Date
Programme started: 05/02/14
Proposal started: 05/02/14
Agreement from client: 13/02/14
Storyboard to be started by: 15/02/14
Production to be started by: 25/02/14
Post-Production to be started by: 20/04/14
Rough-cut to be supplied to client  by: 25/04/14
To be agreed with client by: 27/04/14
Final Version to be completed by: 05/05/14
                                  Date
Completed: 05/02/14
Completed: 05/02/14
Completed: 13/02/14
Completed: 15/02/14
Completed: 27/02/14
Completed: 24/04/14
Completed: 29/04/14
Completed: 27/04/14
Completed: 08/05/14


Production Schedule
Location Visit Sheet

Programme Title: Music Video - Take a Walk
Client: Passion Pit
Writer: Jack Fox
Producer: Jack Fox
Director: Jack Fox
Date: 05/02/14


We will be visiting various locations as the scenery plays a key part within the music video. We are looking for scenes with symmetrical backgrounds as the singer has to be walking towards the camera directly down the middle. If the background is not symmetrical then the singer will look out of place. Locations that we could visit to record this video would be:

London:
London Bridge
St Pauls Cathedral
Buckingham Palace
Piccadilly Circus
Trafalgar Square


Access to location via:

London: 
London Underground
Buses


Health and Safety Issues to note:

London:
Trains can be dangerous
Dangerous driving in London
Poor weather could be unsuitable to film in
Can be dangerous in certain areas at night time


Potential Filming Problems :

May not be allowed to record on certain property
Weather could cause the filming to be unsafe
Batteries could run out of charge whilst filming
People interfering whilst we are trying to film
Cars in the road where we will be standing

Additional Notes:

London:





Production Schedule
Call Sheet


Programme Title: Music Video - Take a Walk
Client: Passion Pit
Writer: Jack Fox
Date: 05/02/14

CREW

Camera: Canon EOS 600D

Production Assistant: Daniel Cole

Transport: Jack Fox/Daniel Cole

Props: Jack Fox/Daniel Cole

Meeting at:

Location Venue: House (Jack Fox's)

CALL DATE: Starting date - 25/02/14

CALL TIME: 10 AM

Transport: Car (Daniel Cole) and/or trains/buses

INSTRUCTIONS: Meet promptly at times arranged. We will be recording throughout many different days so the times/dates will vary. All cast members will be notified well in advance.


Actors: Daniel Cole

Make – up: N/A

Wardrobe: Casual clothing throughout, although some shots will require certain attire

Location Catering: We will need to visit clothing shops before hand to purchase items

Notes: We will also need to purchase props whilst we are out shopping


Production Schedule
Cast and Crew Contact Details


Programme Title: Music Video - Take a Walk
Client: Passion Pit
Writer: Jack Fox
Date: 05/02/14


Name/Role
Mobile Telephone Number
Home Telephone Number
Daniel Cole (actor)
Jack Fox (camera operator)
07423 324 329
07564 955 393
02045 223 1943
02044 356 5347


Contingency Plan
Name: Jack Fox

Production: Music Video - Take a Walk

Potential problems and how to overcome these problems:

There could be many potential problems throughout the recording of this music video although I feel that they can easily be overcome. An example of a potential problem would be getting 'lost' within London. If we are looking for somewhere in particular and cannot find it, then this will be a problem as it will put us behind schedule. Ways to overcome this, though, would be to plan well ahead and ask for any directions if we do find ourselves off course. Another problem could be the battery for the camera running out. A way to make sure this does not happen would be to make sure the battery is fully charged and bring the spare battery for the camera. Also, I would take the charger so that I could ask to charge the drained battery at a shop/restaurant. If, in case it rains, we feel that it is unsafe to film then we will cancel filming and resume another day. We can always check in advance what the weather will be like though to make sure there is no chance of poor weather.




Risk Assessment
Group Members: Location:
Hazard
Person(s) at Risk
Likelihood of Hazard
1 – Extremely Unlikely
5 – Extremely Likely
Severity of Hazard Outcomes
1 – Very Low Risk
5 – Very High Risk
Risk Level
(Likelihood + Severity)
2
Measures to Take to Manage Risk
Risk Managed?
Y/N
Trains
Jack Fox Daniel Cole
2
5
7
Make sure we stand behind the yellow line

Poor weather
Jack Fox
3
1
4
Do not use the camera if it end up wet

Motorists
Jack Fox Daniel Cole
3
3
6
Look when crossing road, use crossings

Dangerous areas
Jack Fox Daniel Cole
2
3
5
Make sure to stay in well lit areas



Contacts

Emergency Service: 999
Robert Clack School:
 020 8270 4222


Production Budget


Item
Cost
Clothing
Props                                                 
Travel
Accomodation
Food/Drink
                      


£0
£5
£40
£0
£10

Total Production Budget
£55



Costumes and Props

Character Name: Daniel Cole

Costume:
Variety of clothing that was previously purchased so we  didn't need to buy any new clothes to wear.







Props: 
Variety of props that we already had or made including items such as a wedding doll, tin can, phones, banana, flowers, cardboard sign amongst others. 